The chart shows a firm’s complete time-and-task schedule for the marketing team, planning team, and development team involved in the launching of a new product.
Based on the information in the graph, select from each drop-down menu the option that creates the most accurate statement.
To the nearest 5 percent, the number of weeks the development team has at least one task scheduled is percent of the total duration represented by the chart.
Week is the only week during which three different tasks are scheduled to begin.