Constraints
A manager of an apartment building in Ankara, Turkey, is planning the building's maintenance budget for the next three years—Y1, Y2, and Y3. All maintenance must be paid for from the building's maintenance reserve account (MRA). The manager knows that at the end of the current year (Y0), there will be exactly 50,000 lira (₺) in the MRA.
The apartment owners have set the following priorities and constraints for the manager.
Draft Plan
The table shows the manager's draft maintenance plan. For each project and year, the corresponding cell indicates the amount of money to be spent on the project in that year. A blank cell indicates that, in this plan, no money is to be spent on the indicated project in the indicated year. There are no other projects.
For each of the following years, select Yes if, according to the MRA projections for the manager's draft plan, the end-of-year balance in the MRA meets the owners' constraints as described in the Constraints tab. Otherwise, select No.
YES | NO | |
---|---|---|
|
|
Y1
|
|
|
Y2
|
|
|
Y3
|